a building engineering services association jct standard building contract 2016 changes on 31 october 2016 the jct published a new edition of its standard building contract with the changes listed ...

icon picture PDF Filetype PDF | Posted on 13 Sep 2022 | 3 years ago
Partial capture of text on file.
                    A
          BUILDING ENGINEERING
            SERVICES ASSOCIATION
        JCT STANDARD BUILDING CONTRACT 2016 
        CHANGES
        On 31 October 2016 the JCT published a new edition of its Standard Building Contract with the changes 
        listed below. The update including new definitions and The Construction Design and Management 
        Regulations (CDM) are now incorporated into the construction contract.
        1. PAYMENT PROVISIONS (SIMPLIFIED):
              Dz  Combined Payment Notice and Pay Less Notice and final dates for payment.
              Dz  Interim valuation dates which apply throughout the construction period and the rectification period payments now 
                 will be every month rather than every two months. 
              Dz  14-day period applies to both the period of time between the due date and the final date for payment for interim 
                 and final payments. 
              Dz  New procedure for prompt assessment within 28 days by the employer of loss and expense claims and 14 days from 
                 each subsequent monthly update from the Contractor. 
              Dz  Fluctuations Options A, B and C were made more flexible and are set out and selected in the Contract Particulars. 
                 Options B and C are no longer attached to the contract but are still available to use form the JCT website and the 
                 contract now allows for an alternative bespoke cost adjustment formula. 
        2. EXISTING STRUCTURE AND INSURANCE 
             A new insurance Option C available to permit alternative solutions to the problems and allows the parties to set out their 
             own bespoke insurance arrangements. 
             It is also optional to include an optional product liability insurance instead of professional indemnity insurance (the required 
             type is to be specified in the Subcontract Particulars).
        3. INTERIM VALUATION DATE (IVD) 
             Introduced in all editions to permit an option to specify it prior to the commencement of work on site (must be specified 
             in the Contract Particulars regardless of A or B option applies). 
             The due date for payment is 7 days after the IVD, or if the contractor’s interim payment application is submitted later 
             than the IVD, 7 days after the employer’s receipt of the interim payment application.
        LEGAL & COMMERCIAL                                                                                              1 OF 3
             legal@theBESA.com           020 7313 4919           www.theBESA.com             @BESAGroup           BESA Group
        Lincoln House 137-143 Hammersmith Road, London W14 0QL
      JCT STANDARD BUILDING CONTRACT 
      February 2017
      4. NEW LOSS AND EXPENSE ASCERTAINMENT PROCEDURE
          A new procedure that requires for the prompt notification of loss and expense claims and submission of supporting 
          information by Subcontractors. The contractor has 42 days to carry out an initial assessment of the loss and expense 
          incurred and 28 days to carry out further assessments following the submission of any supporting information by the 
          Subcontractor.
      5. CONSENT AND APPROVALS 
          Requires that consent or approval of either the employer or the contractor shall not be unreasonably delayed or withheld 
          (except consent to assignment). Those seeking to amend must be mindful of the above requirement.
      6. THIRD PARTY RIGHTS AND COLLATERAL WARRANTIES
           Dz  There is now ability to add personalised documentation detailing particulars.
           Dz  Now includes a net contribution clause however, in many cases, the Contract is amended to give the Contractor total 
             design responsibility, so a net contribution clause will not be appropriate in those circumstances and will need to be 
             deleted (if the Employer chooses to use the JCT Third Party Rights schedules).
           Dz  Option for Subcontractors to provide rights to beneficiaries either by way of collateral warranties or third party rights.
           Dz  States the parties’ rights to terminate and vary the Subcontract where third party rights have been granted. 
      7. COPYRIGHT LICENCE
          Expressly assignable to any owner from time to time of the works and may be sub-licenced to any owner or tenant of 
          the Works.
      8. SITE MANAGER
          The Contractor is required to appoint a full time site manager not just a person in charge and need consent of the Employer 
          to approve the identity of the site manager and any replacement.
      9. PUBLIC CONTRACTS REGULATIONS 2015 – REFLECTS IN JCT 
           Dz  The new provisions allow public authorities to comply with requests made under the Freedom of Information Act 2000. 
           Dz  Fair Payment principles and 30-day payment rule. 
           Dz  Incorporation of Building Information Modelling (BIM) which leaves parties to decide upon the terms and develop 
             their own bespoke documentation.
      LEGAL & COMMERCIAL                                                                      2 OF 3
          legal@theBESA.com     020 7313 4919      www.theBESA.com      @BESAGroup        BESA Group
      Lincoln House 137-143 Hammersmith Road, London W14 0QL
      JCT STANDARD BUILDING CONTRACT 
      February 2017
      10. PERFORMANCE BONDS AND PARENT COMPANY GUARANTEES 
          (PCGS) 
          Requirement for the contractor to provide a performance bond or/and a PCG on the execution of the contract where the 
          contract particulars allow for optional expiry dates of the bonds being either; 
           Dz  The date of practical completion 
           Dz  2 weeks after the expiry of the rectification period 
           Dz  The date for issue of the notice of completion of making good       
      LEGAL & COMMERCIAL                                                                      3 OF 3
          legal@theBESA.com     020 7313 4919      www.theBESA.com      @BESAGroup        BESA Group
      Lincoln House 137-143 Hammersmith Road, London W14 0QL
The words contained in this file might help you see if this file matches what you are looking for:

...A building engineering services association jct standard contract changes on october the published new edition of its with listed below update including definitions and construction design management regulations cdm are now incorporated into payment provisions simplified combined notice pay less final dates for interim valuation which apply throughout period rectification payments will be every month rather than two months day applies to both time between due date procedure prompt assessment within days by employer loss expense claims from each subsequent monthly contractor fluctuations options b c were made more flexible set out selected in particulars no longer attached but still available use form website allows an alternative bespoke cost adjustment formula existing structure insurance option permit solutions problems parties their own arrangements it is also optional include product liability instead professional indemnity required type specified subcontract ivd introduced all edi...

no reviews yet
Please Login to review.