                                  Dated                                               20 
                                                               
                                                               
                                            (1) UNIVERSITY OF SOUTHAMPTON 
                                                               
                                                            and 
                                                               
                                                     (2) [CONTRACTOR] 
                                                               
                                                               
                                                               
                                                 BUILDING CONTRACT  
             incorporating the terms of the JCT Standard Building Contract (Without Quantities) (2016) 
                                for the construction of [                                  ] 
                                          at [                                  ] 
                                                               
                                                               
                                                               
                                                               
                                                               
                                                               
                                                               
                                                               
                                                               
                                                               
                                                     48 Chancery Lane          
                                                     London WC2A 1JF 
                                                   DX: 193 Chancery Lane 
                                                 Telephone: 020 3319 3700 
                                                enquiries@keystonelaw.co.uk 
                                                   www.keystonelaw.co.uk  
            JCT Standard Building Contract for University of Southampton v3 (April 2019) 
              
              
                                                  Joint Contracts Tribunal 
                          Standard Building Contract Without Quantities 2016  
                                                                       
              
             This Agreement is made the                                                                      20 
             This Agreement records the terms of a contract made between the parties identified as the Contractor and 
             Employer below.  The Agreement incorporates the conditions and supplemental conditions of the JCT 
                                                                                                  1
             Standard  Building  Contract  [Without  Quantities]  [with  Contractor’s  Design]   2016  Edition  (the  “JCT 
             Contract") as amended by the following provisions and schedules.   
             This Agreement sets out the entire agreement and understanding of the Parties and supersedes all prior 
             oral or written agreements, understandings or arrangements relating to the subject matter of this contract.   
             This Agreement shall not be amended, modified or supplemented except in writing by duly authorised 
             representatives of both Parties. 
              
                                                              AGREEMENT 
              
             Employer           UNIVERSITY OF SOUTHAMPTON (a company incorporated by Royal Charter under 
                                number RC000668) of Highfield, Southampton, Hampshire SO17 1BJ 
              
             Contractor         [CONTRACTOR] (registered in England and Wales under company                            ) 
                                whose registered office is at                                                  
                                                           
              
              
                                                                RECITALS 
              
             First              The Employer wishes to have the following work carried out: 
                                                                                                      (the “Works”); 
                                and has had drawings and either a specification or work schedules prepared which show 
                                and describe the work to be done; 
              
             Second             the  drawings  and  specifications  setting  out  details  of  the  Works  (the  “Contract 
                                Drawings”) are annexed to this Contract and identified in the Contract Particulars; 
              
                                                              
             1
               Delete as appropriate and amend relevant Recitals and Articles accordingly. 
                                                                                                                              1 
             JCT Standard Building Contract for University of Southampton v3 (April 2019) 
                
               Third                In accordance with whichever of the following options and documents is stated in the 
                                    Contract Particulars to apply, the Contractor either: 
                                         (A) has priced the Specification or Work Schedules (the “Priced Document”), the 
                                              total of such pricing being the Contract Sum stated in Article 2 (“Pricing Option 
                                              A”); or 
                                         (B) has stated the sum he will require for carrying out the Works shown on the 
                                              Contract  Drawings  and  described  in  the  Specification,  that  sum  being  the 
                                              Contract Sum stated in Article 2, and has supplied to the Employer a Contract 
                                              Sum Analysis or a Schedule of Rates on which that sum is based (the “Priced 
                                              Document”) (“Pricing Option B”); 
                                    and has provided the Employer with the priced schedule of activities annexed to this 
                                    Contract (the “Activity Schedule”); 
                                    the Priced Document, the priced Activity Schedule, where provided, and (where Pricing 
                                    Option B applies) the (unpriced) Specification are annexed to this Contract and identified 
                                    in the Contract Particulars; 
                
               Fourth               for the purposes of the Construction Industry Scheme (CIS) under the Finance Act 2004, 
                                    the status of the Employer is, at the Base Date, as stated in the Contract Particulars; 
                
               Fifth                the Employer has provided the Contractor with a Schedule (the “Information Release 
                                    Schedule”) which states the information the Architect/Contract Administrator will release 
                                    and the time of that release; 
                
               Sixth                the division of the Works into Sections (if any) is as identified in the Contract Particulars; 
                
               Seventh              where  so  stated  in  the  Contract  Particulars,  this  Contract  is  supplemented  by  the 
                                    Framework Agreement identified in those particulars; 
                
               Eighth               whether any of the Supplemental Provisions 1 to 6 and 9 apply is stated in the Contract 
                                    Particulars;  
                
                      2
               Ninth                the Works include the design and construction of: 
                                                                                                                                        
                                    (the “Contractor’s Designed Portion”) 
                
               Tenth                the  Employer  has  supplied  to  the  Contractor  documents  showing  and  describing  or 
                                    otherwise stating his requirements for the design and construction of the Contractor’s 
                                    Designed Portion (the “Employer’s Requirements”) 
                
               Eleventh             in  response  to  the  Employer’s  Requirements  the  Contractor  has  supplied  to  the 
                                    Employer: 
                                             documents showing and describing the Contractor’s proposals for the design and 
                                              construction  of  the  Contractor’s  Designed  Portion  (the  “Contractor’s 
                                              Proposals”); and 
                                                                
               2
                 The Ninth to Twelfth Recitals apply only where there is a Contractor’s Designed Portion 
                                                                                                                                                2 
               JCT Standard Building Contract for University of Southampton v3 (April 2019) 
                
                                             an  analysis  of  the  portion  of  the  Contract  Sum  relating  to  the  Contractor’s 
                                              Designed Portion (the “CDP Analysis”); 
                
               Twelfth              the Employer has examined the Contractor’s Proposals and, subject to the Conditions, is 
                                    satisfied  that  they  appear  to  meet  the  Employer’s  Requirements.    The  Employer’s 
                                    Requirements, the Contractor’s Proposals and the CDP Analysis are identified in the 
                                    Contract Particulars; 
                
                
                                                                         ARTICLES 
                
               Article 1             Contractor’s Obligations 
                                     The Contractor shall carry out and complete the Works in accordance with the Contract 
                                     Documents. 
                
               Article 2             Contract Sum 
                                     The Employer shall pay the Contractor at the times and in the manner specified in the 
                                     Conditions the VAT exclusive amount of £[                            ] (the "Contract Sum") 
                                     or such other sum as becomes payable under this Contract’. 
                
               Article 3             Architect/Contract Administrator 
                                      For the purposes of this Contract the Architect/Contract Administrator is   
                                                         of                                                                             or,    if 
                                     he ceases to be the Architect/Contract Administrator, such other firm or person as the 
                                     Employer nominates in accordance with clause 3.5 of the Conditions. 
                
               Article 4             Quantity Surveyor 
                                     For the purposes of this Contract the Quantity Surveyor is/the functions of the Quantity 
                                     Surveyor shall be exercised by                                                           of  
                                                                                                           or,  if  he  ceases  to  be  (or  to 
                                     exercises  the  functions  of)  the  Quantity  Surveyor,  such  other  firm  or  person  as  the 
                                     Employer nominates in accordance with clause 3.5 of the Conditions. 
                
               Article 5             Principal Designer 
                                     The  Principal  Designer  for  the  purposes  of  the  CDM  Regulations  is  the 
                                     Architect/Contract Administrator or                                             of       
                                                                                                 or such replacement as the Employer 
                                     at any time appoints to perform that role. 
                
               Article 6             Principal Contractor 
                                     The Principal Contractor for the purposes of the CDM Regulations is the Contractor or 
                                     such replacement as the Employer at any time appoints to perform that role. 
                
               Article 7             Adjudication 
                                     If  any  dispute  or  difference  arises  under  this  Contract,  either  Party  may  refer  it  to 
                                                                                                                                                3 
               JCT Standard Building Contract for University of Southampton v3 (April 2019) 
The words contained in this file might help you see if this file matches what you are looking for:

...Dated university of southampton and building contract incorporating the terms jct standard without quantities for construction at chancery lane london wca jf dx telephone enquiries keystonelaw co uk www v april joint contracts tribunal this agreement is made records a between parties identified as contractor employer below incorporates conditions supplemental edition amended by following provisions schedules sets out entire understanding supersedes all prior oral or written agreements understandings arrangements relating to subject matter shall not be modified supplemented except in writing duly authorised representatives both company incorporated royal charter under number rc highfield hampshire so bj registered england wales whose office recitals first wishes have work carried works has had drawings either specification prepared which show describe done second specifications setting details are annexed particulars delete appropriate amend relevant articles accordingly third accordanc...

no reviews yet
Please Login to review.