Applications Guide
MasterFormat GROUPS, SUBGROUPS, AND DIVISIONS
PROCUREMENT AND CONTRACTING FACILITY SERVICES SUBGROUP
REQUIREMENTS GROUP Division 20 – Reserved for Future Expansion
Division 00 – Procurement and Contracting Division 21 – Fire Suppression
Requirements Division 22 – Plumbing
Introductory Information Division 23 – Heating, Ventilating, and Air Conditioning
Procurement Requirements (HVAC)
Contracting Requirements Division 24 – Reserved for Future Expansion
Division 25 – Integrated Automation
Division 26 – Electrical
SPECIFICATIONS GROUP Division 27 – Communications
Division 28 – Electronic Safety and Security
GENERAL REQUIREMENTS SUBGROUP Division 29 – Reserved for Future Expansion
Division 01 – General Requirements SITE AND INFRASTRUCTURE SUBGROUP
Division 30 – Reserved for Future Expansion
FACILITY CONSTRUCTION SUBGROUP Division 31 – Earthwork
Division 02 – Existing Conditions Division 32 – Exterior Improvements
Division 03 – Concrete Division 33 – Utilities
Division 04 – Masonry Division 34 – Transportation
Division 05 – Metals Division 35 – Waterway and Marine Construction
Division 06 – Wood, Plastics, and Composites Division 36 – Reserved for Future Expansion
Division 07 – Thermal and Moisture Protection Division 37 – Reserved for Future Expansion
Division 08 – Openings Division 38 – Reserved for Future Expansion
Division 09 – Finishes Division 39 – Reserved for Future Expansion
Division 10 – Specialties PROCESS EQUIPMENT SUBGROUP
Division 11 – Equipment Division 40 – Process Interconnections
Division 12 – Furnishings Division 41 – Material Processing and Handling
Division 13 – Special Construction Equipment
Division 14 – Conveying Equipment Division 42 – Process Heating, Cooling, and Drying
Division 15 – Reserved for Future Expansion Equipment
Division 16 – Reserved for Future Expansion Division 43 – Process Gas and Liquid Handling,
Division 17 – Reserved for Future Expansion Purification, and Storage Equipment
Division 18 – Reserved for Future Expansion
Division 19 – Reserved for Future Expansion Division 44 – Pollution and Waste Control Equipment
Division 45 – Industry-Specific Manufacturing
Equipment
Division 46 – Water and Wastewater Equipment
Division 47 – Reserved for Future Expansion
Division 48 – Electrical Power Generation
Division 49 – Reserved for Future Expansion
19 Introduction and Applications Guide
DIVISION 01
NUMBER TITLE EXPLANATION
DIVISION 01 – GENERAL
REQUIREMENTS
01 00 00 General May be used as Division level
Requirements Section title.
01 10 00 Summary
01 11 00 Summary of Work
Includes: description of construction delivered under a single
contract. Description of provisions for future construction.
May Include: list of products ordered in advance, owner-
furnished products, salvaged material and equipment, products
delivered to owner, and owner-installed products.
Alternate Terms/Abbreviations: purchase contract: procurement
contract: purchase order.
See: 00 24 00 for procurement scopes.
00 54 13 for agreement form supplementary scope statement.
01 31 00 for coordination of work under a single contract.
01 64 00 for owner-supplied products.
01 11 13 Work Covered by Contract Documents
01 11 16 Work by Owner
01 11 19 Purchase Contracts
01 12 00 Multiple Contract Summary
Includes: description of construction delivered under more than
one construction contract; for example, multiple prime,
construction management, and design-build. Summary of
contracts, related prior construction, related concurrent
construction, contract interface, phasing of construction, and
temporary facilities and controls responsibility.
May Include: list of products ordered in advance, owner-
furnished products, salvaged material and equipment, products
delivered to owner, and owner-installed products, future
construction, and provisions for future construction associated
with each contract.
See: 00 24 00 for procurement scopes.
00 54 13 for agreement form supplementary scope statement.
01 31 16 for multiple contract coordination.
61 Master List of Numbers, Titles, and Explanations
DIVISION 01
NUMBER TITLE EXPLANATION
01 12 13 Summary of Contracts
01 12 16 Work Sequence
01 12 19 Contract Interface
01 14 00 Work Restrictions
Includes: restrictions that affect construction operations.
Location of construction, occupancy requirements, and use of
premises and site.
See: 01 53 00 for temporary construction related to access and
use of site.
01 55 00 for temporary vehicular access and parking.
01 56 00 for temporary barriers and enclosures.
01 14 13 Access to Site
01 14 16 Coordination with Occupants
01 14 19 Use of Site
01 14 33 Work in Rights-of-Way
01 18 00 Project Utility Sources
Includes: information concerning utility companies providing
permanent services to the project.
See: 01 51 00 for temporary utilities.
01 18 13 Utility Service Connections
Notes: this is the location to specify information necessary for
connecting utilities and where connection is made by utility.
01 20 00 Price and Payment Procedures
01 21 00 Allowances
Includes: administrative and procedural requirements for cash
and quantity allowances for products, installation, testing, and
contingencies. Time allowances. In a project manual
application, other titles affected by allowances should reference
this title.
May Include: allowance amounts and descriptions.
See: 00 70 00 for conditions of the contract for allowance
requirements.
See Also: 00 24 00 for procurement scopes for allowance
amounts and items.
00 40 00 for allowances included in procurement forms.
00 43 21 for allowances procurement form supplement.
00 54 21 for allowances schedule agreement form supplement.
Master List of Numbers, Titles, and Explanations 62
DIVISION 01
NUMBER TITLE EXPLANATION
01 21 13 Cash Allowances
01 21 16 Contingency Allowances
01 21 19 Testing and Inspecting Allowances
01 21 23 Installation Allowances
01 21 26 Product Allowances
01 21 29 Quantity Allowances
01 21 43 Time Allowances
01 22 00 Unit Prices
Includes: administrative and procedural requirements for unit
prices and measurement and payment.
May Include: list and description of unit price items.
See Also: 00 24 00 for procurement scopes for unit price
descriptions.
00 40 00 for unit prices included in procurement forms.
00 43 22 for unit price procurement form supplement.
00 54 22 for unit prices schedule agreement form supplement.
01 22 13 Unit Price Measurement
01 22 16 Unit Price Payment
01 23 00 Alternates
Includes: administrative and procedural requirements for
alternate bids or proposals. Includes submission and
acceptance procedures.
May Include: list and description of each alternate.
Alternate Terms/Abbreviations: alternates: alternatives: bid
items.
See Also: 00 24 00 for procurement scopes for alternate
descriptions.
00 40 00 for alternates included in procurement forms.
00 43 23 for alternates procurement form supplement.
01 24 00 Value Analysis
Includes: administrative and procedural requirements for value
analysis, application for consideration, and consideration of
proposals.
May Include: appropriate forms.
Alternate Terms/Abbreviations: value analysis: value
management: value improvement.
See: 00 63 00 for modification forms.
01 26 00 for contract modification procedures.
63 Master List of Numbers, Titles, and Explanations