168x Filetype XLSX File size 0.03 MB Source: gnssn.iaea.org
Sheet 1: Original
From | To | Durat. | Activity | Participants | Outcome/deliverables |
T0-3 y | T0-2 y | - | Request for IRRS | host | IAEA plans and initiates the mission |
T0-24 m | T0-18 m | 1-2 days | Information Meeting | IAEA, host and all stakeholders | IAEA provides initial information on the mission and also training on self-assessment, indication of the time when mission takes place |
T0-15 m | T0-12 m | 2-3 m’s | Preparations for self-assessment | Host and stakeholders | Project plan |
T0-12 m | T0-9 m | 3-9 m’s | Self-assessment | host and all stakeholders – counterparts are responsible | SA Report, List of non-compliances, Action Plan |
T0-9 m | T0-6 m | 1-2 days | Prep Meting | IAEA, host and all stakeholders | Scope is fixed, Policy Issues selected, Schedule agreed (including visits) |
T0-6 m | T0-3 m | 1 m | Preparation of ARM | Host | ARM – Remark: schedule preparation of ARM |
T0-3 m | T0-2 m | 1 day | Sending out ARM to IAEA | Host management, | ARM received by the IAEA |
T0-9 m | T0 | Within that period | Resource planning: | Project group | Booking of hotel rooms and assigning rooms at the regulator |
T0-5 m | T0 | Within that period | Resource planning: | Project group | Room for entrance meeting for IRRS team and hosts (30+ people) |
T0-5 m | T0 | Within that period | Resource planning: | Project group | Room(s) for Exit meeting + press conference facilities, PR staff is engaged |
T0-9 m | T0 | Within that period | Resource planning: | Project group | Administrative support will be available all the time |
T0-9 m | T0 | Within that period | Resource planning: | Project group | Emergency exercise planned and organized |
T0-9 m | T0 | Within that period | Resource planning: | Staff involved | Not allow absences for the time of the mission |
T0-5 m | T0 | Within that period | Resource planning: | Project group | IT resources including IT staff are planned and informed, and supplied or booked for the time of IRRS mission |
T0-5 m | T0 | Within that period | Resource planning: | Project group | Communication arrangements discussed, analysed and finalized |
T0-5 m | T0 | Within that period | Resource planning: | Project group | Catering organized |
T0-5 m | T0 | Within that period | Resource planning: | Project group | Transport organized including visits and social events |
T0-5 m | T0 | Within that period | Resource planning: | Project group | Visits agreed with stakeholders including licensees |
T0-5 m | T0 | Within that period | Resource planning: | Project group | Inspection visits organized |
T0-1 m | T0-2 w | 1-2 hrs | Organize meeting/briefing for all hosts staff | All hosts staff | Hosts' staff is informed about the objectives, conduct, scope of the mission – in general terms |
T0-2 m | T0-2 w | Within that period | Mission planning: | Project group | Ensure availability of all relevant documents |
T0-2 m | T0-2 w | Within that period | Mission planning: | Project group | Information flow within the host organization is planned, senior staff is familiar with that |
T0-2 m | T0 | Within that period | Mission planning: | Project group | Efficient re-scheduling of changes is organized and means to inform all interested persons are in place |