Yanchep District Open Space |
|
|
|
|
|
Pavilion |
|
Sources: |
|
DCWC Yanchep Open Space Cost Plan Report (Schematic Design) - December 2015 (16/109128) |
|
|
|
FECA (m2) |
737 |
UCA (m2) |
926 |
GFA (m2) |
1663 |
|
|
Amenities Building Works |
$2,663,000 |
External Works |
$244,000 |
External Services |
$180,000 |
Preliminaries |
$393,000 |
|
|
Design Contingency |
$279,000 |
Construction Contingency |
$188,000 |
Public Art |
Excl |
Fit out |
Excl |
Building Surveyour Levy & Fee |
$13,000 |
Consultant Fees |
$119,000 |
|
|
Escalation to end 2016 |
$36,000 |
|
|
Minus identified cost savings |
-$715,000 |
Estimated Project Cost |
$3,400,000 |
|
|
|
|
Oval Landcaping Works |
|
Sources: |
|
Yanchep Open Space Ovals Cost Report - Design Development Report November 2015 (15/576184) |
|
|
|
Actual Costs |
|
|
|
Concept designs, cost estimates and site investigations |
|
Life Cycle Costing (WT Partnership Australia Pty Ltd) |
$2,200 |
Squire Patton Boggs |
$6,842 |
Cardno (WA) Pty Ltd |
$12,430 |
Cost Planner (DCWC Pty Ltd) |
$15,500 |
Design Development (Lycopodium Infrastructure) |
$121,867 |
Rider Levitt Bucknall WA Pty Ltd |
$8,750 |
Installation of Irrigation Bore (Rond Drilling) |
$35,992 |
|
|
Internal Administration & Project Management |
|
Project Management & Overheads (City of Wanneroo) |
$182,498 |
Tender Advertising (Marketforce) |
$384 |
Tender Advertising (Tenderlink) |
$175 |
Tender Courier (Toll Transport) |
$212 |
|
|
Sub-Total Actual Expenditure |
$386,850 |
|
|
Estimated Costs |
|
PRE-TENDER CONSTRUCTION COST ESTIMATE |
|
Preliminaries |
|
Groundworks |
|
Drainage |
|
Roads & Pavements |
$3,839,344 |
Landscape |
|
Hydraulic Services |
|
Electrical Services |
|
|
|
Design contingency |
|
Construction contingency |
$383,934 |
Professional Fees |
|
Building Surveyor Levy & Building Permit |
N/A |
Client Cost |
Excl |
Project Management Fees |
$91,115 |
|
|
Escalation |
|
Plus Retsining and Landscaping works from Pavilion, and additional associated works |
$500,000 |
Winter Plantign Works |
$600,000 |
|
|
|
|
Sub Total Estimated Expenditure |
$5,414,393 |
|
|
Estimated Project Cost |
$5,801,244 |
|
|
|
|
Oval Groundworks |
|
Sources: |
|
Council Report CR05-05/15 Yanchep Active Open Space - Oval Groundworks Costs |
|
RJ Vincent Variation Order - Rock Surface Rectification Works Quote 14/1/2016 |
|
|
|
Bulk Earthworks |
$2,211,931 |
Rock Rectification Works |
$449,219 |
Estimated Project Cost |
$2,661,150 |
|
|
|
|
Land Acquisition |
|
Sources: |
|
IVWA Land Valuation 8/12/2015 (15/596029) |
|
|
|
Land Cost Estimate (128,034m2 @ 49.98/m2 |
$6,400,000 |
Estimated Project Cost |
$6,400,000 |
|
|
|
|
|
|
|
|
YANCHEP DISTRICT OPEN SPACE - Summary |
|
Land Acquisition |
$6,400,000 |
Oval Groundworks |
$2,661,150 |
Oval Development |
$5,801,244 |
Pavilion |
$3,400,000 |
TOTAL ESTIMATED PROJECT COST - Yanchep District Open Space |
$18,262,394 |
|
|
|
|
|
|
|
|
|
|
Capricorn Coastal Node |
|
|
|
|
|
Sources: |
|
Community Facilities at Alkimos Eglinton and Yanchep-Two Rocks Development Contribution Plans - Cost Report (Business Case), March 2016 |
|
|
|
Building Cost |
$- |
External Works |
$1,091,523 |
External Services |
$336,730 |
|
|
Allowance for 5 star design (4%) |
$- |
Preliminaries (10%) |
$142,825 |
Locality Loading |
$39,277 |
|
|
Contingencies (Planning, Design, Construction) |
$345,000 |
Professional Fees & Disbursements |
$239,781 |
|
|
Escalation to end 2017 |
$38,553 |
|
|
Land Area & Rate |
|
Land Cost Estimate |
|
|
|
TOTAL ESTIMATED PROJECT COST - Capricorn Coastal Node |
$2,233,689 |
|
|
|
|
|
|
|
|
|
|
Yanchep Surf Life Saving Club |
|
|
|
|
|
Actual Costs |
|
|
|
Concept designs, cost estimates and site investigations |
|
* Preliminary Cost Estimate on original concept (DCWC) |
$1,750.00 |
* Concept Design for YSLSC (Bollig Design group) |
$35,436.00 |
* Power Load Calculation (BCA Consultants) |
$900.00 |
* Stormwater Drainage Concept Design & Cost Estimate (Maclean & Lawrence) |
$14,700.00 |
* Permeability Testing (Qualcon Laboratories) |
$1,099.99 |
* Geotechnical Report for YSLSC site (SGS Australia) |
$16,112.00 |
* Drainage Design and Cost Estimate (Porter Consulting Engineers) |
$9,810.00 |
* Design audit & compliance (Corporate Scorecard) |
$299.00 |
* Design Development (Lycopodium) |
$198,690.00 |
|
|
|
|
Coastal Studies & DA Costs |
|
* Coastal Assessment Study (UWA) |
$24,900.00 |
* Coastal Hazard Risk Management Adaptation Plan (Cardno) |
$44,649.00 |
* Titile Search (Landgate/Department of Lands)) |
$977.00 |
|
|
Siteworks & Services |
|
* Site retaining wall as a component of Brazier Road Extension (Ertech ) **EXCLUDED** |
$281,126.82 |
* Hydraulic Services (Ertech ) |
$175,673.00 |
* Hydraulic Services Administration (R J Vincent) |
$27,506.00 |
* Boom lift hire (Coastes Hire) |
$313.38 |
* Traffic Control (Total Road Service) |
$1,000.00 |
* Traffic Control (Vigilant Traffic Management) |
$320.00 |
* Traffic Management Signage (Road Signs Australia) |
$602.80 |
* Demolition works (Nateis Contracting) |
$8,350.00 |
* Water supply and waste water contribution; water main connection fee (Water Corporation) |
$10,920.00 |
* Power Supply (Western Power) |
$73,129.00 |
* Survey for Western Power Services (Ognesis) |
$550.00 |
* Service Location (FindWise Location Services) |
$360.75 |
* Earthmoving (Mayday Earthmoving) |
$1,504.50 |
* Dilapidation survey (Bradbury Sewell Pty Ltd) |
$786.00 |
* Nastech WA Pty Ltd |
$3,260.00 |
|
|
|
|
Internal Administration and Project Management |
|
* Project Management & Overheads (City of Wanneroo) |
$265,163.24 |
* Tender advertisement for Detailed design & documentation |
$780.61 |
* Tender advertising for construction (Tenderlink) |
$525.00 |
* Tender Couriers (Toll Transport) |
$126.73 |
|
|
|
|
Sub-Total Actual Expenditure |
$920,194.00 |
|
|
Estimated Costs |
|
|
|
Design Development (Tender Cost - Lycopodium Infrastructure) |
$63,665.00 |
Power Supply (Cost Estimate - VDM Condulting) |
$- |
Sewer Pump Station (Cost Estimate - Maclean & Lawrence) |
$- |
Stormwater Drainage to comply with WAPC requirement of 1:100 year storm event (Cost Estimate - Porter Engineering / RBB) |
$- |
Tender Advertising & Signage |
$- |
Construction of YSLSC (Cost Estimate - RBB) |
$4,986,930.00 |
Car Park Construction (Cost Estimate - City of Wanneroo Infrastructure Services) |
$- |
Construction and Project Management Costs |
$150,000.00 |
Rehabilitation Works |
$212,500.00 |
Cost Associated with CHRMAP requirements |
$400,000.00 |
|
|
|
|
Sub-total Estimated Expenditure |
$5,813,095.00 |
|
|
Estimated Project Cost |
$6,733,289.00 |
Contingency Sum on non tender works |
$100,000.00 |
TOTAL ESTIMATED PROJECT COST - Yanchep Surf life Saving Club |
$6,833,289.00 |
|
|
|
|
|
|
Costs include: |
|
* Entire carpark adjacent to SLSC location |
|
* 120m of Brazier Road retaining wall immediately adjacent to the east of SLSC footprint and carpark |
|
* Services from Beachaven Drive to the SLSC site and only servicing the club. Additional service costs for Fisherman's Hollow not included. |
|
* Coastal protection works for the SLSC |
|
* Stormwater drainage for SLSC |
|
* Design, site preparation and construction |
|
* Project Management costs |
|
|
|
Costs Exclude: |
|
* All works for Brazier Road realignment, including roundabout |
|