RENCANA ANGGARAN BIAYA
BANTUAN RUANG PRAKTEK SISWA (RPS)
APBN 2018
PEKERJAAN/BANTUAN : RUANG PRAKTEK SISWA (RPS)
NO PERJANJIAN : 11387/D5.4/KU/2018
SEKOLAH : SMK PIJAR ALAM
SPESIFIKASI : BANGUNAN BERTINGKAT
SUMBER DANA : APBN 2018
HARGA SATUAN JUMLAH SATUAN
NO. URAIAN Unit JUMLAH
BAHAN TENAGA BAHAN TENAGA
I PEKERJAAN PERSIAPAN
1 Bedeng + Bouplank 1 ls 3,100,000 1,801,000 3,100,000 1,801,000
2 Listrik dan air kerja 1 2,500,000 1,000,000 2,500,000 1,000,000
Jumlah Sub Pekerjan PERSIAPAN 5,600,000 2,801,000 8,401,000
II PEKERJAAN GALIAN DAN URUGAN
1 Galian Tanah Pancang 4 bh 200,000 800,000
Manual 30 x 30 x 300
2 Galian Tanah Pondasi 120 x 120 4 bh 150,000 600,000
3 Galian Tanah Pondasi 100 x 100 6 bh 150,000 900,000
4 Galian Tanah Sloof 30 x 50 58 m' 40,000 2,320,000
5 Urugan Kembali 1.00 ls 1,000,000 1,000,000
6 Urugan Lantai ± 20 cm tanah dari luar 132 2 45,000 25,000 5,940,000 3,300,000
m
Jumlah Sub Pekerjaan GALIAN dan URUGAN 5,940,000 8,920,000 14,860,000
III PEKERJAAN PONDASI
3
1 Pancang Manual 135 kg/m 4 bh 646,000 181,000 2,584,000 724,000
3
2 Pondasi 120 x 120 123 kg/m 4 bh 706,000 266,000 2,824,000 1,064,000
3
3 Pondasi 100 x 100 140 kg/m 6 bh 482,000 198,000 2,892,000 1,188,000
Jumlah Sub Pekerjan PONDASI 8,300,000 2,976,000 11,276,000
IV PEKERJAAN SLOOF
3
4 SLOOF Gantung 110 kg/m 42 m' 466,000 133,000 19,572,000 1,006,000
Jumlah Sub Pekerjan PONDASI dan SLOOF 19,572,000 1,006,000 20,578,000
V PEKERJAAN KOLOM + BALOK
3
1 Kolom 30 x 50 116 kg/m 10 bh 1,849,000 281,000 18,490,000 2,810,000
3
2 Kolom 30 x 30 /Selasar 105 kg/m 4 bh 1,409,000 200,000 5,636,000 800,000
3
3 Balok Induk 25 x 40 240 kg/m 44 m' 576,000 101,000 25,344,000 4,444,000
3
4 Balok Anak 20 x 30 231 kg/m 24 m' 379,000 59,000 9,096,000 1,416,000
3
5 Lisplang Selasar 20 x 40 183 kg/m 12 m' 474,000 68,000 5,688,000 816,000
Jumlah Sub Pekerjan KOLOM dan BALOK 64,254,000 10,286,000 74,540,000
3 2
VI PEKERJAAN PLAT BETON 100 kg/m 130 m 381,000 67,000 49,530,000 8,710,000 58,240,000
VII PEKERJAAN DINDING
1 Pasangan Bata 1 : 4 102.9 2 53,800 40,000 5,537,000 4,116,000
m
2 Plesteran dan Acian 205.8 2 17,000 65,000 3,499,000 13,377,000
m
Jumlah Sub Pekerjan DINDING 9,036,000 17,493,000 26,529,000
VIII PEKERJAAN KUSEN DAN DAUN
1 Kusen Pintu 1 bh 800,000 100,000 800,000 100,000
2 Kusen Jendela 15 lb 400,000 75,000 6,000,000 1,125,000
3 Daun Pintu 2 bh 750,000 200,000 1,500,000 400,000
4 Daun Jendela 15 bh 250,000 50,000 3,750,000 750,000
5 Pekerjaan Gantungan 6 set 150,000 25,000 900,000 150,000
Jumlah Sub Pekerjan KUSEN DAN JENDELA 12,950,000 2,525,000 15,475,000
2
IX PEKERJAAN PLAFON 131 m 71,000 50,000 9,301,000 6,550,000 15,851,000
Unit HARGA SATUAN JUMLAH SATUAN
NO. URAIAN JUMLAH
BAHAN TENAGA BAHAN TENAGA
X PEKERJAAN LANTAI 131 2 91,000 30,000 11,921,000 3,930,000 15,851,000
m
XI PEKERJAAN FINISHING
1 Cat Tembok 205.8 2 5,000 25,000 1,029,000 5,145,000
m
2 Cat Plafon 131 2 5,000 30,000 655,000 3,930,000
m
3 Cat Kayu 25 2 12,000 20,000 300,000 500,000
m
5 Instalasi Listrik 4 Titik 300,000 200,000 1,200,000 800,000
Jumlah Sub Pekerjan FINISHING 3,184,000 10,375,000 13,559,000
JUMLAH DANA KONSTRUKSI 275,160,000
374,805,630
XII PERENCANAAN DAN PENGAWASAN
1 Biaya Perencanaan (3 % x Biaya Konstruk 8,254,000
2 Biaya Pengawasan (2% x Biaya Konstruks 5,503,000
JUMLAH 13,757,000
III BIAYA PENGELOLAAN
Biaya Pengelolaal Administrasi (2 % x Biaya Konstruksi) 2,751,000
JUMLAH 2,751,000
Resume :
Biaya Pekerjaan Konstruksi 275,160,000
Biaya Perencanaan dan Pengawasan 13,757,000
Biaya Pengelolaan Administrasi 2,751,000
Jumlah Biaya Yang Dikeluarkan 291,668,000
Bekasi, Desember 2018
Kepala SMK PIJAR ALAM
Dody Lusianawati, S.Pd
NIP. -
1,801,000 1.8%
1,000,000 1.3%
3.05%
0.3%
0.2%
0.3%
0.8%
0.4%
3.4%
5.40% 8,920,000
1.2%
1.4%
1.5%
4.10% 2,976,000
7.5%
7.48% 1,006,000
7.7%
2.3%
10.8%
3.8%
2.4%
27.09% 10,286,000
21.17% 8,710,000 21.2%
3.5%
6.1%
9.64% 17,493,000
0.3%
2.6%
0.7%
1.6%
0.4%
5.62% 2,525,000
5.76% 6,550,000 5.8%
5.76% 3,930,000 5.8%
0.0%
2.2%
1.7%
0.3%
0.7%
4.93% 10,375,000
275,160,000 75,572,000 100.0%