jagomart
digital resources
picture1_Fidic Yellow Book Pdf 201459 | Variation Provisions 2017


 167x       Filetype PDF       File size 0.19 MB       Source: corbett.co.uk


Fidic Yellow Book Pdf 201459 | Variation Provisions 2017

icon picture PDF Filetype PDF | Posted on 10 Feb 2023 | 2 years ago
Partial capture of text on file.
      Variation Provisions in the FIDIC Yellow Book 2017 
      Written by Roger Button1
      Introduction                                                Temporary Works being those which are required 
      Much has already been written concerning                    on the site for the execution of the Works6. Both of 
      the new FIDIC forms of contract published                   these definitions therefore appear to restrict “the 
      in December 2017. They are approximately                    Works” to activities which take place on the site. 
      50 % longer and sought to set out the                       A definition of’ Variation’ solely by reference to 
      various procedure in much greater detail                    changes in “the Works” has the potential to pose 
      with the object of both encouraging good                    difficulties in the case of a design and build 
                                                                  contract such as the Yellow Book since the precise 
      practice and reducing the scope for                         nature of much of the Works will, subject to the 
      disputes. Numerous minor amendments                         Employer’s Requirements and approval by the 
      have also been made.                                        Engineer, be at the discretion of the Contractor. 
      The purpose of this article is to look in more              Such a definition enables the Engineer on behalf of 
      detail at the provisions dealing with                       the Employer to instruct changes to “the Works” to 
      Variations, these being amongst the most                    the extent that these are specified in the Contract, 
      frequently scrutinised in practice.                         probably in the Employer’s Requirements. 
                                                                  What the Engineer may wish to do in such 
      Definition of ‘Variation’                                   circumstances is to change the performance criteria 
      In the previous 1999 Yellow Book, a ‘Variation’ is          with which the completed works must comply or 
      defined as any change in the Works or in the                the basis on which that performance is measured.  
      Employer’s Requirements which is instructed or              There is now, however, scope for doubt as to 
      approved on behalf of the Employer pursuant to              whether under the 2017 form the right of the 
                                         2                        Employer to vary includes making these kind of 
      other provisions in the Conditions .  Accordingly, if       changes as opposed simply to ordering changes to 
      the Employer were to wish to change, for example,           the Works themselves.
      the performance criteria for the Works, he could do 
      so by means of an appropriate change in the                 The Right to Object to a Variation 
      Employer’s Requirements.  
                                                                  The 2017 Yellow Book provides for the Engineer to 
      The position under the 2017 Yellow Book is less             initiate a Variation at any time before the Issue of a 
      straightforward. The definition of “Variation”                                      7
                                                                  Taking-Over Certificate.   This may be done by 
      simply refers to changes in “the Works”, the                means of an instruction pursuant to Sub-Clause 
      reference to the Employer’s Requirements being              13.3.1 or a request to the Contractor for a proposal 
      omitted3
               . “The Works” are defined as the                   in each case issued by the Engineer. 8 
      Permanent Works and the Temporary Works or 
      either of them.4 The Permanent Works are in turn            In most cases, a Variation will be regarded by the 
      defined as being those of a permanent nature which          Contractor as a welcome development. There may 
      are to be executed by the Contractor5, the                  be cases, however, in which the Contractor may 
      1
        Roger Button is a Consultant with Corbett & Co International Construction Lawyers Ltd 
      2
        Sub-Clause 1.1.1.5 
      3
        Sub-Clause 1.1.88 
      4
        Sub-Clause 1.1.89 
      5
        Sub-Clause 1.1.65 
      6
        Sub-Clause 1.1.82 
      7
        Sub- Clause 13.1 
      8
        Sub–Clause 13.3 
                                                                                             Tel: + 44 (0)20 8614 6200 
                                                                                             Fax: + 44 (0)20 8614 6222 
      Variation Provisions - FIDIC Yellow Book 2017/RB       1                               Email: info@corbett.co.uk 
      2018(10)/3/CLAL                                                                       www.corbett.co.uk 
      wish to oppose the Variation because, for example,                 the efforts which the Contractor will need to 
      it might be difficult to implement or might have a                 make to secure the item and the likely effect 
      detrimental effect on the performance of his other                 of these factors on the overall progress of 
      obligations under the Contract.                                    the execution of the Variation and the 
      In the case of a Variation by means of an                          Works; 
      instruction, the Contractor is bound by the                    (c) that the proposed Variation will adversely
      Variation instructed unless the Contractor                         affect the Contractor’s ability to comply with
                                                                                                         13
      promptly gives a notice contesting the Variation                   its health and safety obligations  under the
      with detailed particulars on certain specific                      Contract and those relating to the
      grounds. These differ from those found in the 1999                 protection of the environment14. There is a
      Yellow Book and are also more extensive.9                          corresponding provision in the 1999 Yellow
                                                                         Book15 but the new provision is in
      The grounds for objection in the 2017 Yellow Book                  considerably wider terms. This ground of
      are as follows:                                                    objection is largely self – explanatory. It
                                                                         should be noted is the Contractor would
          (a) that the varied work was Unforeseeable                     need to demonstrate that compliance with
              having regard to the nature and scope of the               these obligations has become significantly
              work described in the Employer’s                           more difficult or risky but not that such
              Requirements. “Unforeseeable” is defined                   compliance would become impossible;
              as being unforeseeable by an experienced               (d) that the proposed Variation will have an
              contractor as at the Base Date which, in                   adverse impact on the achievement of the
              turn, is defined as being a date 28 days                   Schedule of Performance Guarantees. There
              before the latest date for the submission of               is an almost identical provision in the 1999
              the tender.10  This has no equivalent in the
              Yellow Book 1999. If the proposed Variation                Yellow Book.16 Again, this ground envisages
              is of a kind which could not have been                     that the achievement of the Performance
              foreseen as a realistic possibility at the Base            Guarantees would be rendered more
              Date, the objection will have been made out;               difficult by the proposed Variation rather
                                                                         than completely impossible.
          (b) that the Contractor cannot readily obtain              (e) that the proposed Variation may adversely
              the Goods required for the purpose. There is               affect the Contractor’s obligation contained
              a similar provision in the 1999 Yellow                     in Sub-Clause 4.1 to complete the Works so
              Book.11 “Goods” are widely defined. 12                     that they will be fit for the purpose(s) for
              The effect of this wide definition is in broad             which they are intended as defined in the
              terms that, if the Contractor cannot readily               Employer’s Requirements.17
              obtain any item required to execute the                    It should be noted that, in contrast to the
              proposed Variation, this ground of objection               grounds in sub-paragraphs (c) and (d)
              will have been made out. The question of                   above, the Contractor does not need to
              whether the Contractor cannot readily                      demonstrate that the proposed Variation
              obtain the item in question may depend on                  will render the performance of the
              the amount of time required to obtain the                  Contractor’s obligation under Sub-Clause
              item, the amount of time normally required,
      9                                                           14
        See Sub-Clause 13.1, Sub-paragraphs (a) – (e)               Sub-Clause 4.18 
      10 Sub-Clause 1.1.87                                        15 Sub-Clause 13.1 Second Paragraph Sub-Paragraph (ii). 
      11Sub-Clause 13.1 Second Paragraph Sub -paragraph (i)       16 Sub-Clause 13.1 Second Paragraph Sub-Paragraph (iii). 
      12 Sub-Clause1.1.44                                         17 Sub-Clause Sub-Clause 4.1(first paragraph) 
      13 Sub-Clause 4.8 
                                                                                             Tel: + 44 (0)20 8614 6200 
                                                                                             Fax: + 44 (0)20 8614 6222 
      Variation Provisions - FIDIC Yellow Book 2017/RB       2                               Email: info@corbett.co.uk 
      2018(10)/3/CLAL                                                                       www.corbett.co.uk 
              4.1 more difficult but merely that it may do 
              so. This difference is presumably because           Nothing is stated expressly in Sub-Clause 3.5 as to 
              the Contractor’s obligation as to fitness for       the basis on which the Engineer is to make his 
              purpose is of such fundamental importance           decision but the intention plainly is that, if the 
              that even the risk of increased difficulty is       Engineer is satisfied that the Contractor’s challenge 
              sufficient to justify an objection.                 to the instruction is well founded in fact, he is to 
                                                                  either to reverse or vary the instruction. 
      The Engineer’s Response                                     Variation Procedure 
      The fourth paragraph of Sub-Clause 13.1 of the              The procedure immediately following the issue of a 
      2017 Yellow Book requires the Engineer, promptly            Variation instruction in the 2017 Yellow Book 
      after receipt of the Contractor’s Notice and                19does not differ markedly from that in the 1999 
      supporting particulars, to respond by cancelling,           Yellow Book. In each case, the Contractor must 
      confirming or amending the Variation instruction.           supply a
      If the Engineer considers the Contractor’s objection                  description of the varied work including 
      to be factually incorrect, he will confirm the              (in the case of the 2017 Yellow Book) details of the 
      instruction. If, on the other hand, he regards the          resources and methods to be adopted, a 
      objection as justified in whole or in part, he will         programme for the execution of the Variation and 
                                                                  the Contractor’s proposals for the modification of 
      either cancel the instruction or, if possible, vary it      the overall project programme and the completion 
      so as to accommodate the grounds of the objection.          date for the project. The last of these may well, of 
      In some cases at least, the Contractor will wish to         course, involve a claim for an extension of time. 
      challenge the decision of the Engineer either to            Most importantly, the Contractor must also 
      confirm a Variation instruction or to modify it in          produce a proposal for the adjustment of the 
      ways which the Contractor regards as                        Contract Price with supporting particulars. 
      unsatisfactory. At that point, consideration will           The 1999 Yellow Book requires all of this 
      need to be given to the provisions of the Yellow            information to be produced as soon as practicable. 
      Book 2017 dealing with the resolution of disputes.          The 2017 Yellow Book is more specific by 
                                                                  stipulating a period of 28 days of the instruction or 
      Variation or Not?                                           such other period as may be proposed by the 
      There may be instances in which the Contractor              Contractor and agreed by the Engineer. 
      considers that what purports to be simply an                Valuation of Variations 
      instruction issued by the Engineer is in fact a 
      Variation. In these circumstances, the 2017 Yellow          The 1999 Yellow Book contained little guidance on 
      Book introduces a new procedure for resolving this          the valuation of Variations and numerous 
      kind of dispute18. The Contractor must immediately          arguments and disputes arose. This deficiency is 
      and before commencing work on the instruction               made good in the 2017 Yellow Book20 which 
      give a notice to the Engineer of his position with          provides for alternative bases of valuation 
      reasons. The Engineer must respond within seven             depending on whether or not a Schedule of Rates 
      days of the notice confirming, varying or reversing         and Prices (‘Schedule’) forms part of the contract. 
      the instruction. If he fails to do so, the Engineer will 
      be deemed to have revoked the instruction.                  If a Schedule is included, the rate or price for an 
      Otherwise, the Contractor is bound by the                   item in the Schedule, will be that for the same item 
      Engineer’s response and must comply with the                forming all or part of the Variation. If there is no 
      instruction.                                                rate or price for an item in the Schedule, the rate or 
      18 Sub-Clause 3.5                                           20 Sub-Clause 13.3.1 
      19 Sub-Clause 13.3.1 
                                                                                              Tel: + 44 (0)20 8614 6200 
                                                                                             Fax: + 44 (0)20 8614 6222 
      Variation Provisions - FIDIC Yellow Book 2017/RB        3                               Email: info@corbett.co.uk 
      2018(10)/3/CLAL                                                                        www.corbett.co.uk 
       price for similar work will apply. This is however           of the Contractor’s cost of preparing a proposal for 
       subject to the qualification that a new rate or price        a Variation at the request of the Engineer which has 
       may be applied if no rate or price for an item is            been subsequently rejected by the Engineer 
       specified in the Schedule and no rate or price is            requires a formal notice under Sub-Clause 20.2.24 
       appropriate because the work in question is not of a         The same is true of claims by the Contractor for 
       similar character or is not executed under similar           additional time and money as a result of changes in 
       conditions as any item in the Contract.                      Laws.25 
       If a new rate or price is required, then this is             Omissions 
       derived from any relevant item in the Schedule with 
       reasonable adjustments taking into account “all              The Yellow Book 1999 made it clear that the 
       relevant circumstances”.  If there is no relevant            Employer was not allowed to omit work so that it 
       rate or price, then these are derived from the Cost          could be undertaken by others. The 2017 Yellow 
       Plus Profit of executing the Work. ‘Cost’ is defined         Book contains a provision in similar terms but 
       as all costs reasonably incurred in undertaking the          expressly provides for an agreement between the 
       work whether on or off site together with                    Employer and the Contractor to the contrary. In the 
       overheads, taxes and similar charges.21 ‘Profit’ is          event of a contrary agreement, there is an express 
       defined as the percentage stated in the Contract             provision for the Contractor to include a claim for 
       Data or five per cent in default.22                          loss of profit and/or damages suffered or to be 
                                          
                                                                    suffered as a result of the omission. This would be 
       A further welcome new provision is to be found in            part of the details particulars of the Variation 
       the final paragraph of Sub-Clause 13.3.1 of the 2017         required by Sub-Clause 13.3.1. The particulars 
       Yellow Book. This requires the Engineer to assess a          including this information are considered by the 
       provisional price or rate for the varied work for the        Engineer and the issue resolved either by 
       purpose of including a sum on account of the value           agreement or the Engineer’s determination. 
       of the Variation in interim payments pending final 
       resolution of that value by agreement or                     Variation by Request for Proposal 
       determination. 
                                                                    The 1999 Yellow Book gave the Engineer the option 
       Finally, it should be borne in mind that, under the          of seeking a proposal from the Contractor before 
       2017 Yellow Book, the Engineer no longer acts on             instructing a Variation. The 2017 Yellow Book 
       behalf of the Employer (as under the 1999 Yellow             contains a similar process but with more detailed 
       Book) but instead adopts a neutral position                  provisions. 
       between the parties.23 As a result, it is now open to 
       the Employer to challenge the Engineer’s valuation           The Contractor is not entitled to a separate 
       of a Variation, if so minded.                                payment for the cost of the preparation of the 
                                                                    proposal except in circumstances in which the 
       Notices                                                      proposal is not accepted. As mentioned, a formal 
                                                                    notice of claim under Sub-Clause 20.2 is required 
       The Yellow Book 2017 makes it clear that the                 as a precondition to entitlement. 
       Contractor is entitled to an extension of time and 
       an adjustment to the Contract Price for a Variation          Value Engineering 
       without giving formal notice of his claim to the 
       Engineer pursuant to Sub-Clause 20.2. It should be           The 1999 Yellow Book provides for the Contractor 
       noted, however, that certain other claims under              to prepare (at his own expense) a proposal for a 
       Clause 13 do require a formal notice. Thus payment           variation which would accelerate Completion, 
       21 Sub-Clause 1.1.19                                         24 Sub-Clause 13.3.2 (last paragraph). 
       22 Sub-Clause 1.1.20 – Definition of ‘Cost Plus Profit’      25 Sub-Clause 13.6 
       23 Sub-Clause 3.7 – first paragraph. 
                                                                                                 Tel: + 44 (0)20 8614 6200 
                                                                                                Fax: + 44 (0)20 8614 6222 
       Variation Provisions - FIDIC Yellow Book 2017/RB         4                                Email: info@corbett.co.uk 
       2018(10)/3/CLAL                                                                          www.corbett.co.uk 
The words contained in this file might help you see if this file matches what you are looking for:

...Variation provisions in the fidic yellow book written by roger button introduction temporary works being those which are required much has already been concerning on site for execution of both new forms contract published these definitions therefore appear to restrict december they approximately activities take place longer and sought set out a definition solely reference various procedure greater detail changes potential pose with object encouraging good difficulties case design build such as since precise practice reducing scope nature will subject disputes numerous minor amendments employer s requirements approval have also made engineer be at discretion contractor purpose this article is look more enables behalf dealing instruct variations amongst most extent that specified frequently scrutinised probably what may wish do circumstances change performance criteria previous completed must comply or defined any basis measured instructed there now however doubt approved pursuant whethe...

no reviews yet
Please Login to review.