300x Filetype PDF File size 1.64 MB Source: eia.emb.gov.ph
PROJECT DESCRIPTION FOR SCOPING
300 MW Diesel Power Plant Project
Ingrid2 Power Corporation
Barangay Batangas II, Mariveles, Bataan
Submitted to:
Environmental Management Bureau – Central Office
February 2020
•
An Environmental Report By:
Unit 8L-M, Future Point Plaza 3
111 Panay Avenue, South Triangle
Rizal City, Metro Manila
Tel. No.: (02) 442-2830
Submitted To:
Department of Environment and Natural Resources
Environmental Management Bureau –
Central Office
EMB Building, DENR Compound, Visayas Avenue
Diliman, Quezon City
DOCUMENT TRACKING
Versio Report Compiled By: Checked By: Approved By:
n No. Name Signature Name Signature Date
1 K.G. Bartolome J.M. Lim J.M.
Lim
Distribution of Latest Version
No. of Submitted To: Date Submitted Received By: Remarks:
Copies
February 2020
Table of Contents
1.0 PROJECT DESCRIPTION ................................................................................................... 1-1
1.1 Project Location and Area ....................................................................................... 1-2
1.1.1 Accessibility of the Project Site ...................................................................................................... 1-2
1.1.2 Project Impact Areas ...................................................................................................................... 1-2
1.2 Project Rationale .................................................................................................... 1-8
1.3 Project Alternatives ................................................................................................ 1-9
1.3.1 Site Selection .................................................................................................................................. 1-9
1.3.2 Technology/Design Selection ......................................................................................................... 1-9
1.3.3 Resources ....................................................................................................................................... 1-9
1.4 Project Components.............................................................................................. 1-11
1.5 Process/Technology .............................................................................................. 1-12
1.5.1 Major Components: Modular Diesel Generators ......................................................................... 1-12
1.5.2 Auxiliary Facilities ......................................................................................................................... 1-13
1.5.3 Pollution Control Facilities ........................................................................................................... 1-13
1.5.4 Plant Operation and Maintenance ............................................................................................... 1-14
1.6 Project Size ........................................................................................................... 1-14
1.7 Development Plan, Description of Project Phases, and Corresponding Timeframes . 1-15
1.7.1 Pre-Construction .......................................................................................................................... 1-15
1.7.2 Construction ................................................................................................................................. 1-15
1.7.3 Operation ..................................................................................................................................... 1-15
1.7.4 Decommissioning/Abandonment/Rehabilitation ........................................................................ 1-15
1.8 Manpower ............................................................................................................ 1-17
1.9 Project Cost .......................................................................................................... 1-17
1.10 Preliminary Identification of Environmental Impacts .............................................. 1-17
Table of Tables
Table 1-1: Basic Information on the Proposed Project, Proponent, and EIA Preparer ................................... 1-1
Table 1-2: Landmarks and Structures Adjacent to the Proposed Project Site ................................................ 1-2
Table 1-3: Area Allocation of the Proposed Project Components ................................................................ 1-11
Table 1-4: Tentative Project Development and Implementation Timeline .................................................. 1-16
Table 1-5: Manpower Requirement per Project Phase ................................................................................ 1-17
Table of Figures
Figure 1-1: Vicinity Map of the Proposed Project Site ................................................................................... 1-4
Figure 1-2: Technical Coordinates of the Proposed Project Site ........................... Error! Bookmark not defined.
Figure 1-3: Accessibility Map of the Proposed Project Site ............................................................................ 1-5
Figure 1-4: Aerial Photograph of the Proposed Project Location ................................................................... 1-6
Figure 1-5: Direct and Indirect Impact Areas of the Proposed Project ........................................................... 1-7
Figure 1-6: Modular Diesel Power Plant Technology ................................................................................... 1-10
Figure 1-7: Plant Layout Plan for the Proposed Project ........................................ Error! Bookmark not defined.
Figure 1-8: General Site Layout Plan for the Proposed Project ............................. Error! Bookmark not defined.
INGRID2 POWER CORPORATION
300-MW DIESEL POWER PLANT PROJECT
Brgy. Batangas II, Mariveles, Bataan PROJECT DESCRIPTION FOR SCOPING
1.0 PROJECT DESCRIPTION
Ingrid2 Power Corporation (the “Proponent”) will be developing a 300 MW modular diesel engine
power plant (the “Generation Facility”) in Barangay Batangas II, Mariveles, Bataan.
The Generation Facility will be composed of multiple modular diesel engine units and is planned
to be connected via an approximately 1-kilometer transmission line to TeaM Energy’s 230 kV
Bataan Substation which is directly connected to the NGCP 230 kV Limay Substation.
The Proponent is required to secure an Environmental Compliance Certificate (ECC) from the
DENR-EMB prior to any development in the project site. Pre-requisite to the acquisition of an ECC
for a project of this scale is the preparation of an Environmental Impact Statement (EIS), as stated
in Annex A Item No. 3.2.4 (Other Thermal Power Plants e.g., coal, diesel, bunker, etc. with total
power generating capacity equal to or greater than 30 MW) of the EMB Memorandum Circular
005-2014 (“Revised Guidelines for Coverage Screening and Standardized Requirements under the
Philippine EIS System”).
Table 1-1 provides some basic information regarding the proposed project, the Proponent, and
the Environmental Impact Assessment (EIA) preparer.
Table 1-1: Basic Information on the Proposed Project, Proponent, and EIA Preparer
Project Name 300 MW Diesel Power Plant Project
Project Location Brgy. Batangas II, Mariveles, Bataan
Project Area 6 hectares
Project Type Diesel-Fired Power Plant
Project Size/Capacity 300 megawatts
INGRID2 Power Corporation
Office Address: 4/F, 6750 Office Tower, Ayala Avenue, Ayala Center, Makati City
Project Proponent Tel. No.: (02) 7730-6300
Authorized Representative:
Atty. Rodrigo M. San Pedro, Jr. (Attorney-In-Fact)
LCI Envi Corporation
Office Address: Unit 8L-M, Future Point Plaza 3, 111 Panay Avenue, South Triangle,
Quezon City
EIA Preparer Tel. No.: (02) 8442-2830 / Fax No.: (02) 8961-9226
Authorized Representative:
Engr. Jose Marie U. Lim (EIA Team Leader)
1-1
no reviews yet
Please Login to review.